June '08
103. Further Cockpit Detailing
104. The Covering Boards


103. Further Cockpit Detailing

Immediately astern of the dash bulkhead, alongside the driver's seat, I have added another length of conduit to transmit one of the battery cables from the batteries under the seat to the motor compartment. (The other one passes under the sole). It finishes behind the speaker box, and from there the cable will need to find its way to the space under the seat, either by passing down through the sole and then up again, or by passing through a tunnel from the cavity it now occupies to the seat space.





The electrical cable conduit behind the lagging.

While the finish on the forward lagging strips is drying, the aft ones are replaced. The fiddle on the rear seat has had its coating of Cetol, and the beading along the starboard edges of the seat is added.



With the near completion of this side, the throttle lever has to be positioned before the strips are glued down. The opening for the glove box in the forward compartment has not yet been cut, because I am not sure whether the throttle mechanism will allow for one. So the next step is to finish that connection, and then build the box.


The throttle lever is added to the lagging, with a backing block, close enough to the intermediate stringer so that limiting stops can
be built into the stringer to prevent the lever from being over extended, and thereby damaging the delicate throttle itself.

Work on the throttle mechanism, however, had to be interrupted: two weeks of steady rain had so humidified the garage that the lagging boards which had not been given a coat of finish began to grow a black mould on their hoop pine components. It was difficult to remove and unsightly, so I felt that I should concentrate on fixing them, and getting a layer of varnish on them, before proceeding with the throttle.

 
Views of the mould on the lagging boards.

So, the port side was quickly disassembled and the boards lined up for sanding and finishing.



Back to the throttle: the difficulty here is to link the throttle pot box with the throttle lever. The distance between them is too short for a standard cable, so some sort of push rod is needed. The connector for the original cable which is supposed to go with the lever is meant for a 10-32 UNF thread, so that seems to be a good size to aim for. Using a length of 10-32 UNF threaded rod, I can screw it into the connector. All that is left is to attach it to the pot box. There are ball joints designed for the engine end of throttle cables, (also with 10-32 UNF threads), but they only allow about 30° of movement, so cannot be mounted on top of the existing pot box lever. The excursion from full ahead to full astern is about 90°. It could be mounted on the side of the pot box lever, but that would require tapping its ball for the thread of the ball joint post. A simpler solution was to use a Heim joint. Again, in order to achieve unrestricted excursion, the Heim was mounted to the side of the existing ball via a hole drilled to accept a small bolt with locking nuts. The threaded rod screws into the Heim, and fine tuning can be achieved by altering the length of the ball-topped lever on the pot box.


The pot box throttle with its lever drilled and a Heim joint fitted. Here it is in the full astern position.


Full ahead position.

Now, all that has to be done is mount the pot box in a suitable location and connect it to the control lever. It is now apparent that there will be room for a glovebox, so the shelf is added, and a hole is cut for it in the lagging.


The shelf for the forward glovebox is installed.

The best location for the pot box turned out to be in the motor compartment. This way is will be accessible, whereas it would not have been behind the cockpit lagging. So an opening is made through the dash bulkhead for the pushrod, and a frame is constructed to hold the pot box, which is then bolted to the bulkhead. The levers on the pot box and the cockpit are both put into neutral position while the rod is connected. Some stops will be required for the main lever so that is is not straining the pot box through overzealous or accidental action, and then the throttle mechanism is up and running.


Showing the pushrod passing from the throttle lever in the cockpit to the pot box in the motor compartment.

In fashioning the stop blocks I was able to make use of the clamp and shim which were provided with the control lever for the purpose of holding the throttle cable. Instead of that task they are perfect for making a metal on metal contact with the lever.


The stop blocks being glued down.

With the lagging replaced temporarily the starboard side is just about complete. The forward glovebox still has to be blackened, and the speaker cord running through it has to be rerouted, but then it is ready for the coaming...at last. Now to the port side!



On the port side I still have to cut the glovebox apertures, build the forward box, glue down the sole panels, connect the bilge pump hose to the through-hull, decide on a strategy for the vent hose from the shaft seal, bring out the power outlet for the refrigerator, oil the forward sole panel and replace the lagging, but now that the starboard side is finished the port will go a lot more quickly. The second side always seems to be easier than the first. I will also run a short piece of conduit from the motor compartment through the space behind the lagging, in case another battery cable route is needed. The one I had intended to use for that purpose has been called into service to transmit the wiring for the bilge pump.

But the first job was to glue down the sole panels, which had not been done on the port. With them in place, the lagging could quickly be replaced and the speakers could be bolted into their correct relationship with their covers. The location of the power outlet could now be determined, and it was put in the third lagging strip forward of the aft speaker cover. From here it will be able to be reached by the cord from the fridge, and by rear seat passengers


Lining the port side of the cockpit, after the sole is glued down.

The final strategy for the shaft seal vent was to take the tubing up through the side cavity to a breather valve on the side deck, just forward of the port window frame. The valve is designed for a fuel tank, but is just the thing for a neat looking outlet for the tubing. In the extremely unlikely event of water running up the tubing to deck level, it will be discharged overboard. This saves having to put reservoir bottles in for overflow, and also allows free air flow into the tubing, so breaking any siphon effect. It will have to be taken one level higher when the second deck skin is applied, so the lagging boards forward of the windscreen will be left unglued until then to allow for re-attachment of the tubing.


The shaft seal vent tubing running up to the breather valve on the side deck.

The forward glovebox has been made to include access to the bilge pump hose outlet, so its space is a bit limited by the hose and through-hull poking into it, but at least this critical piece of equipment will be able to be seen and reached easily.


The forward glovebox space showing the bilge pump hose and the through-hull.

After a good two months of playing around in the cockpit the space is now beginning to look civilised. There are still some small jobs to be done with trim, but this is basically it as far as the lagging is concerned. Time to move on the side coaming and the rest of the deck work, as well as a few electrical jobs.


These photos, taken with flash, reflect the true colour of the woodwork more than the yellowish ones above, which are taken under
mixed fluorescent, incandescent and natural light. The effect pleases me.



Top of Page





104. The Covering Boards

Many of the yachty looking boats aim for a tapered curve on their covering boards, such that they are wider in the mid deck than at the bow or stern, and that is indeed a pleasing look on a yacht. But on a slipper launch the central section of the board has to fill the gap between the coaming and the upper rubbing strake at the gunwale. Although it is curved, it is a constant 170 mm. wide, and to add tapered front and rear ends to a board like that seems out of place to me. The best solution is to use 170 mm. as the width all along the length of the boat, and across its stern.

The critical fit here is the joint between the covering board and the coaming. This is an area where water is likely to pool and enter if the joint is not tight, and although epoxy can be used to fill minor gaps, because there will be a small fillet covering the join line, it cannot be too generous. The fillet has to be small enough not to interfere with the mechanism of the pram hood which will be added later. So, a curved board has to be fitted, to butt up against a curved coaming, and meeting it at an upward, but varying inclination.

Once that is done, scarf joints have to be fashioned to join the central section to the forward and stern sections, which then have to be cut to parallel the curve of the hull, to meet each other at the bow, and to engage the athwartships section at the stern. The whole lot then has to be glued down with minimal gaps to show a clean transition. It should be pointed out, however, that the idea of scarf joints on covering boards was to make them water tight when they constituted the actual decking structure. With ply decks that it not so important, so the scarf joints could be dispensed with. The photos of slipper launches show only butt joints between the covering boards, as far as I can tell. The decision is one of aesthetics.


Butt joints visible on the covering boards just forward of the navigation lights.

Nevertheless, here is a major woodworking challenge. A number of jigs will have to be made, and a lot of time devoted to the job.


Top of Page


Forward to July '08

Back to Ariadne front page
Back to Monthly Progress chart

Back to January '06
Back to February '06
Back to March '06
Back to April '06
Back to May '06
Back to June '06
Back to July '06
Back to August '06
Back to September '06
Back to October '06
Back to November '06
Back to December '06

Back to January '07
Back to February '07
Back to March '07
Back to April '07
Back to May '07
Back to June '07
Back to July '07
Back to August '07
Back to September '07
Back to October '07
Back to November '07
Back to December '07

Back to January '08
Back to February '08
Back to March '08
Back to April '08
Back to May '08

Problems  shows higher resolution shots as well.



Valid HTML 4.01 Transitional